Construction Timeline & Projects

January through April 2012 will be the big, final push for Trinity! Below, please find the big picture of the next few months – details of individual projects will be posted soon. Please stay flexible, as the timeline/project list will ebb and flow!

 

Funding continues to be needed to complete the restoration of Trinity.  Please continue to fundraise to purchase the materials to complete the restoration efforts.

 

January

  • Insulate all exterior walls and ceilings
    •     3000 sq ft of R30 ceiling insulation
    •     1400 sq ft of R14 exterior wall insulation 
  • Drywall all interior/exterior walls and ceilings – approx 800 sheets. (We will be just hanging and hiring a local contractor to finish tape)
  • Finish painting of exterior facade

 

January/February

  • Paint all interior surfaces
  • Install flooring
    •     4500 sq ft of ceramic floor tile
    •     2500 sq ft of laminate flooring
    •     4 shower stalls to be tiled

 

February/March

  • Install all interior doors
  • Install all door and window casings
  • Install base trim
  • Install all plumbing and electrical fixtures
  • Install kitchen cabinets and appliances

 

April – FINAL PUSH to finish everything up!

 

Claiborne Courtyard:

  • Remove the front sidewalk and stairs and replace with brick pavers
  • Grade front lawn
  • Dig and pour a footing for brick and aluminum fence
  • Install aluminum fence
  • Seed front lawn
  • Plant trees and greenery along front church wall

 

Special Projects (more details soon)

  • Brick columns for the fences
  • Weld cages for AC units
  • Build deck on storage room roof to hold AC units

 

APRIL 8 -- EASTER SUNDAY!